GEC Experience

CNRL Fuel Storage Tank
gec1In 2007, GEC Installations erected large fuel storage tanks in Alberta for Canadian Natural Resources Limited (CNRL). The tanks, which are approximately 35 feet high and 85 feet in diameter, are used to store jet fuel. The project took six months to complete and employed up to 200 personnel. Under extremely tight deadlines, GEC was able complete the project on-time with 0 Lost-time Accidents (LTA).

 

 

IPS Froth Treatment Tanks
gec2From April 2006 to January 2008, GEC constructed 14 Inclined Plate Separator (IPS) Tanks at CNRL's Froth Treat Plant in Alberta. The tanks were sub-contracted through Pennecon Energy. Each IPS tank has a capacity of 1 million litres and weighs approximately 137 tonnes. The hopper, which is the bottom of the cone, is 94 feet from the ground. The pre-fabricated materials for the tanks came to GEC in 8 pieces and were assembled modularly in a jig and lifted into its racks with a crane.

The duration of the project was approximately 18 months, employing 200 personnel, with 0 LTA.

CNRL Tank Farm Pipe Fabrication
gec3To complement the IPS Froth Treatment Tanks, GEC installed approximately 5.2 km of piping of various diameters. This project was completed in 8 months, using up to 100 employees, with 0 LTA.